Real costs · paid figures & local estimates

What it actually costs to build a house in Mexico

This isn’t a national average or a builder’s quote. It’s a breakdown from my own self-managed build in San Cristóbal de las Casas, Chiapas.

I’ve marked each line so you can see what I actually paid, what I’ve estimated, and what you should check locally before relying on it. The paid figures are mostly from 2024–26; the land paperwork dates from my 2017–18 purchase.

Use it as a real-world example, not a universal price list.

¿Más cómodo en español? Usa la calculadora en español →

PlaceSan Cristóbal, Chiapas
Prices paidMostly 2024–26
CurrencyMexican pesos (MXN)
RouteSelf-managed
Paid — what this build actually cost me ~ Estimated — worth checking against a local quote

How much does it cost to build a house in Mexico?

Using the costs from my own build (paid mostly in 2024–26) and my estimates for the rest, a modest two-bedroom, two-bathroom, two-storey house of about 200 m² (2,150 sq ft) comes to roughly MX$1.03 million (≈ US$57,000) to move in and MX$1.18 million (≈ US$66,000) fully finished — about US$30 per square foot. That’s self-managed, on a flat, accessible plot, with the land extra; the worked example shows every line.

Before construction

~MX$69,000
Land paperwork, permits and legal fees at my 2017–18 prices — before a single block is laid (excludes the land itself).

Per finished room

~MX$125,000–145,000
Shell, render, floor, door/window and basic electrics — before bathrooms, kitchen, water and land.

Water system

~MX$77,500
Cistern, pump, tank and the plumbing that connects them (deep well not included).

The example includes paperwork, foundations, shell, the slab between the two storeys, finishes, electrics, the house water system and fixtures. Land purchase, a deep well and rainwater catchment are separate. The practical budget below adds 10–20% contingency; your total changes with size, slope, finishes and who manages the build. Dollar figures use roughly MX$18 to the US dollar, the Banco de México rate in October 2026 — check today’s rate.

Build your budget: start with the whole-house example, adjust the quantities and finish level, then add land and any separate water-source project.

From the actual build

Workers hand-digging foundation trenches with rebar columns and a materials truck on a self-built house site near San Cristóbal de las Casas, Chiapas
Hand-dug footings and rebar columns on my build — San Cristóbal de las Casas, Chiapas, 2019.

Field note

I managed this build myself while working full time and living five miles from the site. In the first year I put more than 6,000 miles on my bicycle going back and forth before and after work. That matters because these costs aren’t abstract quotes — they come from being on site often enough to see where money was spent, where it was wasted, and where I could have made better decisions.

A worked example

What a modest 2-bed, 2-bath house costs to build

Assembled from the figures below for a self-managed, two-storey home of roughly six rooms, about 200 m² (2,150 sq ft) of floor. This is an illustration using my numbers — your total will move with size, room count and finish level. It excludes the land purchase itself.

Land paperwork & permits (my 2017–18 costs)~MX$69,000
Footings & ground-floor groundworks~MX$120,000
Shell (obra gris, ~6 rooms × MX$70,000)~MX$420,000
Slab between the storeys (entrepiso, 3 downstairs rooms × MX$19,500)~MX$58,500
Finishes — liveable core (render, windows, paint)~MX$165,000
Finishes — deferrable (floor tiling + doors)~MX$152,000
Electrical~MX$40,000
Water system~MX$77,500
Fixtures & items that are easy to forget~MX$80,000
Move-in subtotal — before floor tiling & doors≈ MX$1.03M
Fully finished — with tiling & doors added≈ MX$1.18M
Practical budget — with 10–20% contingency≈ MX$1.30–1.42M

The move-in lines come to about MX$1.03 million; adding floor tiling and doors brings it to roughly MX$1.18M, and the practical budget adds 10–20% for the overruns, price changes and surprises that come up on most builds. In US dollars, at roughly MX$18 to the dollar (October 2026), that’s about US$57,000 to move in, US$66,000 fully finished and US$72,000–79,000 with contingency.

Move-in vs fully finished. Floor tiling and doors — about MX$152,000 here — are things you add later, room by room, as the budget allows. I’m living in my house now with poured-concrete floors in some rooms and others still without doors, which is why I show a move-in number and a finished number rather than one figure. There’s a full tiling breakdown in the finishes section below.

Flat site assumed. This total is for a level, easily accessible plot. A hillside adds roughly 50% in my estimate — that’s not a formal quote, it reflects the extra levelling, retaining, access difficulty, slower manual work and drainage I dealt with or would now budget for.

Plan your own build

Estimate your build cost and timeline

The figures above are one real build. This estimator lets you shape them to your own plan — choose your rooms, bathrooms and finish level, then either see a full cost range or, starting from what you can spend each month, roughly how long each stage would take. It’s a planning estimate from one self-managed Chiapas build, not a quote.

All figures are in Mexican pesos (MXN) — roughly MX$18 to the US dollar in October 2026 (Banco de México), but check the current rate. Everything assumes you self-manage the build, the baseline these numbers come from.

Start with what you can invest each month and see when you could move in.

MX$/ mo

How much can you set aside each month for materials and labour?

Count each space (bedroom, living room, kitchen…) as one room of about 4×4 m.

More settings

This changes the cost a lot: self-managing can save money, but it takes time and daily attention on site.

A 3 m block wall, rendered on one face, and a simple swing gate (including the structure that holds it) — these are estimates, not figures from a wall or gate I built myself.

To move in
—
liveable core, before floor tiling and doors
Fully finished
—
with tiled floors and doors

About — per m² built · — m²

See the breakdown

A mix of paid figures and practical estimates. It leaves out land paperwork, plans and permits (about MX$69,000 in my worked example). Adjust to your own build; this isn’t a quote.

There’s a Spanish version of this tool: la calculadora en español.

Before the costs

The land you buy can change everything

Before permits, blocks, labour and finishes, it’s worth saying plainly: the plot itself can move the whole cost of the build. I didn’t understand at the start how much the land would control everything that came after it.

The thing I underestimated most wasn’t one dramatic cost. It was how many small decisions turned expensive once the work had already moved past them.

Nothing beats spending time in the place before you buy. I’d meet people already living in the area, ask about different parts of town, and write down my non-negotiables before falling for a plot. I knew I didn’t want to commute downtown by bicycle every day, and I wanted cleaner air than the centre of town — I keep an air-quality sensor that reads PM2.5, and it’s much lower a couple of miles out. What I didn’t expect was the trade-off: out here the air is cleaner, but rainy-season indoor humidity runs higher than in town, which matters for comfort, mould, materials and whether you end up needing a dehumidifier.

The cheapest land isn’t always the cheapest place to build

A plot can look like a bargain and turn expensive once you start solving water, access, slope, drainage or legal status. Before buying, I’d check at least:

  • Is there an escritura pública?
  • Is it private property or ejidal / common land?
  • Is there water, or will you need rainwater catchment or a deep well?
  • Is the plot flat, or will it need levelling, retaining or drainage?
  • Is access good enough for material trucks and workers?
  • Are basic services already nearby?

Each of those can quietly add a large line to the budget. The legal status in particular is worth a proper conversation with a notary or lawyer before any money changes hands. My guide to buying land in Mexico as a foreigner covers what I checked before buying.

01 / Before you build

Land paperwork & permit costs as a foreigner

In my case — buying outside the restricted coastal/border zone — the purchase needed SRE permission and a local lawyer, and I was a permanent resident at the time. Treat that as my experience, not legal advice: the rules vary by property location and restricted-zone status and change over time, so confirm the current requirements with a notary or lawyer for your exact plot. For the current official fee, see SRE’s Article 27 costs and times; the ticked amounts below are what I paid in 2017–18. The land price itself isn’t in this total; near San Cristóbal expect roughly MX$3,000/m² on the outskirts with basic services, up to ~MX$5,000/m² closer to markets and more desirable areas.

Cost breakdown

ItemCostMark
SRE permit for a foreigner to purchase
In my case, via a local lawyer as a permanent resident
MX$4,000
Lawyer — purchase paperwork & land registryMX$30,000
Legal-status verification of the property
Required
MX$650
Land valuation for the registry
Required
MX$600
Planning permission
2% of the assessed land value — not the price you paid
MX$5,622
Architectural plans
Three design meetings with revisions, plus a quote to build it with material quantities — other architects quoted MX$20,000–25,000 for plans alone. Often free if you hire the architect to build — I was offered that; it’s a common incentive
MX$28,000
Land paperwork, permits & plans
Excludes the cost of the land itself
~MX$69,000

How long it takes

From getting permission, signing the contract and paying a deposit to the land being registered in my name took six months. Build that waiting time into your plans, not just the cost.

Before you buy: the legal status is everything

The biggest risk in buying land here isn’t the price — it’s the deed. Land sold without an escritura pública, and ejido land in particular, can mean you don’t legally own what you paid for. I’ve written up the whole thing — deeds, ejido land, the SRE process, finding land and what to check — in buying land in Mexico as a foreigner.

02 / The shell

What one room costs to build in obra gris

Obra gris is the bare grey shell — structure only, no electrics, plumbing or finishes. Below is one 4×4 m standalone room broken down to the block and bag of cement. The footings line is the one that won’t scale simply with room count — the note underneath explains why, and why building upward lowers your average cost per room.

Cost breakdown

ItemCostMark
Footings & site groundworks
Site levelling, trenching & footings (manual) — scales with the ground floor, not total room count
MX$35,000
Cinder blocks
~780 blocks × MX$18
MX$14,000
Labour — laying walls above foundationMX$15,000
Cement — columns, cadena & blockwork
~13 bags × MX$275
MX$3,500
Rebar — columns & cadena
25 units × MX$150
MX$3,750
Roof slab
Rebar MX$6,750 · cement MX$2,750 · wood to support pour MX$4,000 · labour MX$6,000
MX$19,500
Floor slab
Rebar MX$6,750 · cement MX$2,750 · labour MX$3,000
MX$12,500
Sand & stone
2 loads sand, 1 load stone
MX$4,500
Standalone room, shell only~MX$107,750

Why building upward lowers your cost per room

That ~MX$108,000 is a room standing on its own, carrying its full MX$35,000 of footings and site groundworks. In a real house the footings scale with the ground-floor footprint, not the total room count — roughly MX$120,000 for a 3–4 room footprint, or about MX$40,000 per downstairs room. Because most houses here are two-storey, the upstairs rooms sit on that same footprint: each adds shell cost (~MX$70,000) and a slab beneath it (~MX$19,500, built like the roof slab above), but almost no extra footings. So the more you build upward, the lower your average per-room cost falls. Budget footings against your ground floor, ~MX$70,000 of shell for every room, upstairs and down, and ~MX$19,500 of slab under each upstairs room.

From the actual build

Tabique walls of a downstairs kitchen under construction with wooden scaffolding, in front of a stone containing wall on a self-built house site in Chiapas
The shell going up — the downstairs kitchen in tabique, opening onto the patio below the house (not yet built here). The stone wall behind is the back of that patio and doubles as a containing wall. San Cristóbal de las Casas, Chiapas, 2019.

Brick or block: what changes the budget?

Standard cement block was the cheaper wall on my build. Brick looks like the bargain at MX$7 a piece against MX$18 a block, but a square metre of wall takes about 45 bricks against roughly 12 blocks — far more units and mortar — and the walling labour worked out close to double. Leaving brick exposed claws back some of the render cost. I used different materials for different walls; the full cost and comfort comparison is in brick vs block in Mexico.

03 / Finishes

Finishing costs: render, floors, doors, windows & paint

Finishing is where the cost quietly doubles. Render in particular is one of the largest single line items in the whole build — and the figure people forget. Note the render rate is labour only; cement and lime are extra. Rates are per square metre unless stated; whole-house figures are for a ~10×10 m two-storey home.

Cost breakdown

ItemCostMark
Render — exterior (labour)
MX$180–200/m² labour only · whole house ~MX$40,000
MX$40,000
Render — interior (labour)
MX$180–200/m² labour only · 4 walls + ceiling · whole house ~MX$72,000
MX$72,000
Render materials — cement & lime
On top of labour · ½ bag cement per 2m² with a 50% lime mix · ~MX$35/m²
~MX$22,000~
Floor tiling, all-in
~MX$560/m² (tiles ~MX$250 + labour ~MX$260 + adhesive & grout ~MX$50) · ~MX$110,000 for this house · deferrable — full breakdown below
~MX$110,000~
Wooden doors, locally made & installed
MX$7,000 each · typical 6 doors · wood grade is the lever (pine cheapest, pinabeto mid, cypress/”Nuculpat” best) · deferrable
MX$42,000
Window frames
MX$3,000 each (pino abeto, 1×1m) — cypress/”Nuculpat” costs more but lasts
MX$3,000 ea
Window glass
Annealed 6mm, smaller windows; up to MX$30,000 if tempered/large
MX$10,000
Interior paint & sealer
Extrapolated — see calculation below
~MX$12,000–14,000~
Floor & bathroom tiling — the full breakdown

Floor tiling runs about MX$560/m² all-in on my numbers, and the parts move. Basic tiles are MX$150–300/m² — I weighted toward the upper end of basic; budget hard and you can go cheaper, while luxury tiles climb well past this. Labour is around MX$260/m², give or take 20% by tile size: smaller tiles mean more cuts and more work, so they cost more to lay. On top of both, the adhesive and grout to bed and finish the tiles add roughly MX$50/m² — the piece that’s easy to forget. And watch the area that’s actually tiled — a bedroom floor is roughly 30 m², but a bathroom floor is only about 5 m².

Bathrooms are mostly walls, not floor. You can tile nothing (the extreme saving), tile to the ceiling (the maximum), or land in between. My own balance of cost, function and looks: tiles around the shower (about 2.2×2.3 m) plus a band 1.2 m high behind the toilet and sink — roughly 7.2 m² of wall, about MX$3,700 per bathroom on top of the floor. That’s the balance I’d choose again.

All of it is deferrable. I’m living in my house now with poured-concrete floors in some rooms — tiling is one of the easiest things to add later, room by room, as the budget allows.

Painting — the extrapolation

The base figure is real: Saya vinílica Promaster runs MX$2,160 for a 19 L bucket (~MX$114/L). The total wasn’t in the build notes, so here’s the working — adjust the coverage rate to your own walls:

~400 m² interior surface × 2 coats ÷ 10 m²/L = ~80 L ≈ 4–5 buckets ≈ MX$9,000–10,800

Add a sealer coat first (lime render is thirsty) at roughly MX$3,000, giving ~MX$12,000–14,000 in materials for the interior. Coverage on rough or very absorbent render can be a third lower — treat 10 m²/L as optimistic and buy a spare bucket. If you paint it yourself, that’s the whole cost; a painter adds labour on top.

04 / Electrical

Electrical costs: wiring, fixtures & the earth connection

If the mason wires it, expect to pay roughly the per-room figures. A proper electrician for the whole house costs more but does it properly — and they’ll plan two cable routes up a second storey where a mason leaves you with one.

Cost breakdown

ItemCostMark
Electrician — full house wiring (labour)MX$12,000
Wire, switches & sockets (materials)MX$10,000
Earth & street connections (mufa)
Grounding plus the connection to the street supply
MX$5,000
Breaker box & fuses (consumer unit)MX$800
Lighting conduit in roof & walls
Per room, labour + conduit — not in the subtotal below
MX$2,000 /rm
Whole-house electrical
Plus MX$2,000 conduit per room
~MX$27,800

05 / Plumbing & water

Water & plumbing costs: the cistern, the pump & the taps

This is the system people underestimate most. For bathroom supply you choose between CPVC (cut-and-glue, cheap, easy to repair) and TuboPlus (heat-fused, tougher, UV-resistant for roof runs). I used both. The water storage and pumping is the bulk of the cost. I’ve written the whole system up — cistern, pump, gravity feed, the pipe choice and the mistakes I’d avoid — in water system for a house in Mexico.

Cost breakdown

ItemCostMark
Cistern (cisterna), concrete-lined
~10,000 L · MX$20,000 labour + MX$10,000 materials
MX$30,000
Pump
Two types; sized to the cistern-to-roof lift
~MX$3,000~
Plumbing — pump from cistern up to roof tank
Materials + labour
MX$10,000
Plumbing — roof tank to kitchen, 2 baths & boiler
Materials + labour (TuboPlus)
MX$12,000
In-room supply pipework — 2 baths + kitchen
TuboPlus
MX$1,800
Wastewater plumbing, whole house
Very design-dependent
MX$6,000
Rooftop tank — 1,100 L RotoplasMX$3,800
Boilers / water heaters — 3, gas
2 × MX$1,400 de paso + one MX$6,000 hybrid; premium models run to ~MX$25,000
MX$8,800
Boiler connections & 2 shower valves
MX$689 + 2 × MX$700
MX$2,089
Water & plumbing system~MX$77,500

If the land has no water

I bought land with no water connection, so the build cost isn’t complete until you’ve solved water. In my area the two real options were rainwater catchment or a deep well (pozo profundo).

In 2024 a local deep-well company quoted around MX$80,000 to drill, fit the piping, drop in a pump and connect it to the house — that price covered drilling to about 25 m, with an extra cost per metre beyond that. My water table sits around 18 m down, and they’d normally drill a few metres past it so the well keeps producing through the dry season. As a foreign resident, check the permit requirements before drilling a deep well on your property.

06 / Don’t forget these

Hidden costs: the installations almost everyone leaves out of the budget

These rarely appear in a first estimate and then arrive all at once near the end. Most are estimates, marked ~; the ticked gas-system figure is what I paid. Costs vary by finish and supplier, so price them locally — but leaving them off entirely is the most common way a budget overruns.

Cost breakdown

ItemTypicalMark
Kitchen sink + tap, supplied & fitted
Plumbing labour ~MX$2,500; sink unit & tap on top
~MX$4,000–7,000~
Kitchen counter & cabinetry
Concrete-cast counter is cheapest; carpentry much more
~MX$15,000–40,000~
Toilets — the units themselves
Per toilet; wax flange MX$40–600 extra
~MX$1,500–3,000 ea~
Bathroom basins, showers & fittings
Per bathroom, fixtures only
~MX$3,000–8,000 ea~
Gas tank, regulator & hose
30 kg cylinder MX$2,499 · regulator MX$150 · hose ~MX$300 (varies with length)
MX$2,950
Stairs (for a second storey)
Structure; handrails extra — DIY rails saved me 20,000+
~MX$10,000–25,000~
Sealing & crack repair on concrete roof
Fester FT-201 adhesive ~MX$300 + geotextile + roof paint
~MX$2,000–5,000~

07 / Trust

How I worked these numbers out

Because the whole point of this page is that the figures are real, here’s exactly where they come from and what I did to them.

Every figure marked is what I paid on my own build, managing it myself in San Cristóbal — mostly in 2024–26, as the house went up in stages. The exception is the land paperwork, which dates from my 2017–18 purchase. Figures marked ~ are mine to estimate — either I worked them out from my known costs (like the paint) or they’re typical local ranges you should confirm with a quote. I’ve left the arithmetic visible wherever I could so you can swap in your own quantities. Prices are Chiapas-specific and move with inflation and the peso; treat the year as part of the number, and compare the quantities against current local quotes.

08 / Scope

What’s deliberately not on this page

Two things are left out on purpose, not by accident. The land purchase price itself swings too widely by location to fold into a build total — budget it separately at MX$3,000–5,000/m² near San Cristóbal. And the off-grid water systems — rainwater harvesting and greywater filtration — are their own substantial projects with their own payoffs, so they get their own write-up rather than a buried line here.

09 / Questions

Common questions

How much does it cost to build a house in Mexico?

Using the costs from my self-managed Chiapas build (paid mostly in 2024–26) and my estimates for the rest, the two-bedroom, two-bathroom worked example comes to about MX$1.03 million (≈US$57,000) to move in, about MX$1.18 million (≈US$66,000) fully finished, or roughly MX$1.30–1.42 million (≈US$72,000–79,000) with 10–20% contingency, at about MX$18 to the dollar in October 2026. That assumes a flat, accessible plot and excludes the land purchase, a deep well and rainwater catchment. It’s one planning example, not a national average or a contractor’s quote — use the breakdown and calculator above to adapt it to your own house.

How much does it cost to build a house in Mexico per square metre or square foot?

On my worked example, about MX$5,900 per m² of floor, fully finished — roughly US$30 per square foot at MX$18 to the dollar (October 2026). That’s far below the per-square-foot prices you’ll see quoted for turnkey homes in the resort areas, because it’s self-managed (no contractor’s management or margin), finished to a local standard and priced in Chiapas — and it excludes the land. Treat it loosely: it shifts with whether you measure the ground-floor footprint or the floor area across both storeys, with the finish level, and with the slope of the land. I’d still estimate from rooms rather than square metres: about MX$70,000 of shell per room on the footings, plus a ~MX$19,500 slab under each upstairs room, then finishes, water, electrics and legal on top.

What’s the cheapest practical way to build a house in Mexico?

The biggest saving isn’t haggling on materials — it’s building to a habitable stage and finishing later. On my numbers the move-in core came to about MX$1.03 million, against about MX$1.18M fully finished; the gap is floor tiling and interior doors, which you add room by room as money allows. I’m living in mine now with concrete floors in some rooms and no doors on others. Beyond that: build upward rather than outward (the footings are the costly part; upstairs rooms reuse them and add only a slab), do the simple labour yourself where you can — DIY handrails alone saved me over MX$20,000 — and self-manage instead of paying an architect or maestro, if you have the time to be on site.

How long does it take to build a house in Mexico?

Longer than the cost tables suggest, because two clocks run. Before a single block is laid, the land paperwork took me six months from deposit to the deed being registered in my name. Then the build depends on how you pay: a fixed price for the whole job moves fastest, while paying builders weekly — which buys flexibility to change the design as you go — slows progress, and a build can stretch to a couple of years. I self-managed mine while working full time, which stretched it further. Budget the waiting, not just the spending.

Is it cheaper to pay builders weekly or for the whole job?

Weekly pay gives you flexibility to change the design or stop the work, and time to learn — but it incentivises slow progress, and a build can stretch to a couple of years. A fixed price for the whole job moves faster but builders won’t wait around for the electrician or plumber you bring in. Neither is simply cheaper; they suit different amounts of your own time and attention.

What does obra gris mean?

It’s the bare grey shell of the building — foundation, walls, columns, and roof and floor slabs — with no electrics, plumbing, render or finishes. It’s how local builders quote the first phase. On this build, obra gris ran about MX$70,000 per room on top of the foundation.

Do I need an architect?

No — most homes in Chiapas are built without one. You have three routes: hire an architect, hire a maestro de obra — an experienced lead builder who runs the day-to-day site and coordinates the masons for a fee — or manage it yourself. Each trades cost against control and stress. Skipping the architect saves money but means no one is planning the details — lighting, plumbing routes, finishes — unless you do.

Does this cost include the land itself?

No — every total on this page excludes the land purchase, because land prices swing too widely by location to fold in honestly. Near San Cristóbal, budget it separately: roughly MX$3,000/m² on the outskirts with basic services, up to about MX$5,000/m² closer to markets and the more desirable areas. What the worked example does include is the land paperwork — the SRE permit, lawyer, registry, planning permission and plans — which came to about MX$69,000 at my 2017–18 prices, before a single block was laid. The calculator leaves it out.

Can a foreigner buy land and build in Mexico?

In my case, yes. Buying outside the restricted coastal/border zone needed a permit from the SRE, handled by a local lawyer, and I was a permanent resident at the time — roughly MX$4,000 for the permit and MX$30,000 for the lawyer’s paperwork and registry in 2017, and about six months from deposit to the land being registered in my name. Rules differ by location and restricted-zone status and change over time, so confirm the current requirements with a notary or lawyer for your specific property.

Do I need a building permit to build a house in Mexico?

On my build I paid for planning permission, charged at 2% of the assessed land value (not the price I paid) — MX$5,622 in my case, in 2018. That’s separate from the SRE permit a foreigner needs to buy the land, and it’s part of the ~MX$69,000 of paperwork before any block is laid. Requirements and costs vary by municipality and change over time, so check what your local authority (the municipio) wants for your specific plot — this is what one San Cristóbal build cost, not a national rule or legal advice.

How much does it cost to get water on land with no connection?

I bought land with no water connection, so the build wasn’t finished until I’d solved it. In 2024 a local company quoted around MX$80,000 to drill a deep well (pozo profundo) to about 25 metres, fit the piping and pump, and connect it to the house — my water table sits around 18 metres down. The other option is rainwater catchment. As a foreign resident, check the permit requirements before drilling. The full system — cistern, pump, pipe choice and the mistakes I’d avoid — is in water system for a house in Mexico.

Luke Burchell

Written by Luke Burchell

I built and managed the construction of my own house in San Cristóbal de las Casas, Chiapas — coordinating the masons, plumbers, electricians, land paperwork, water systems and finishing work myself, while living locally. The figures here are what it actually cost, shared so you can plan yours from real numbers.

Read my full story →

Last updated · October 2026 · San Cristóbal de las Casas, Chiapas

These are first-hand figures from one self-managed build, shared so you can plan yours with real numbers instead of guesswork. Prices in Mexican pesos, paid mostly in 2024–26 (the land paperwork in 2017–18). Construction costs move quickly — if you’re reading this well after 2026, treat the figures as a structure to update, not a quote.