Building in Mexico · free checklist

House-building budget checklist for Mexico: based on my Chiapas build

The item list behind my cost breakdown for the house I built in Chiapas, from the obvious lines to the easy-to-miss ones: the lime for the render, the street electricity connection, the gas regulator and, on a two-storey house, the slab between the floors.

Tick what your own build needs, then get local quotes for those lines. My prices for each section are on the cost page. One self-managed build, not a contractor’s quote or a national price list.

PlaceSan Cristóbal, Chiapas
BuildSelf-managed
Checklist52 items · 9 sections
✓ Paid itemsMostly 2024–26
Paid on my build ~ My estimate — check locally QUOTE A quote I was given, not paid

How to use it

1 · Select

Tick the lines your build needs

2 · Price

Get local quotes and check what each one includes

3 · Add a margin

Add a contingency; my worked example uses 10–20%

My prices for each section are on the cost page. Your selections save in this browser, and the list prints.

01 · Land paperwork

Land paperwork & permits

Excludes the price of the land itself (section 9).

02 · Site & footings

Site & footings

On my build the footings followed the ground-floor footprint, not the number of rooms. A second storey shared them, but needed its own slab.

From the actual build

Footings being dug by hand for a self-managed house in Chiapas, with rebar for the first columns and a delivery truck behind
Digging the footings by hand on my build. This is the line that scales with the ground floor, not with the number of rooms.

03 · The shell

The shell (obra gris)

What goes into each room’s walls, columns and slabs. A two-storey house also needs the slab between the storeys.

04 · Liveable finishes

Finishes: the liveable core

Render, windows and paint: what you need before you can live in it.

05 · Finishes for later

Finishes you can add later

Floors and interior doors can be phased in room by room after you move in — some of our rooms are still poured concrete.

06 · Electrical

Electrical

Wiring, the street connection and the conduit people leave out.

07 · Water & plumbing

Water & plumbing: the house system

Cistern, pump, roof tank and the plumbing that connects them. A deep well is not included (section 9).

08 · Forgotten extras

Fixtures & the things people leave out

These rarely make a first estimate, then arrive all at once near the end.

09 · Site-dependent

Site-dependent: not in my totals

My cost page leaves these out of the house total on purpose. Tick any that apply to your site.

10 · Your own lines

Your own lines

Anything I haven’t listed. Write it in when you print the list, or add it to the spreadsheet.

The spreadsheet

Get the same checklist as a budget spreadsheet

The same items, with my paid prices and estimates where I have them, a column for yours, and a status for each line as it firms up: ~ estimate, then quote, then ✓ paid. The summary adds a contingency, shows the total in dollars, and tells you how much of your budget is still guesswork.

Email me the spreadsheet

I’ll email you a link to download it (an .xlsx spreadsheet). New subscribers confirm their email address first. Signing up also adds you to my occasional newsletter about building and living in Chiapas. You can unsubscribe at any time.

Questions

Questions about budgeting a house build in Mexico

What should a budget for building a house in Mexico include?

Land paperwork and permits, the footings, the shell, the finishes (the liveable core first, floors and interior doors later), the electrics, the water system and the fixtures that are easy to leave out, plus anything your site needs, such as a well, a perimeter wall or work on a slope. The land itself is a separate line. The list above follows what I had to plan for on my own build in Chiapas.

Which costs are easiest to leave out of a house-building budget?

From my build: the render materials on top of the render labour, the street electricity connection, the kitchen counter and sink, the gas tank and regulator, stairs for a second storey, sealing a concrete roof and, on a two-storey house, the slab between the floors.

How much contingency should I add?

My worked example on the cost page adds 10–20% on top of the line-by-line total, for overruns, price changes and the surprises that come up on most builds.

Does this checklist include the land?

Yes, in section 9, as a line for your own budget. My cost page keeps it out of the house-building totals, because land prices swing too widely to fold in honestly. The land paperwork and permits are in section 1.

Luke Burchell

Written by Luke Burchell

I self-managed the construction of my own house in San Cristóbal de las Casas, Chiapas, and kept the receipts. This checklist is the item list behind my cost breakdown.

Read my full story →

Last updated · October 2026 · San Cristóbal de las Casas, Chiapas

From one self-managed build in Chiapas, not a quote or a national price list. The ✓ badges mark costs I paid on my build, mostly in 2024–26 (the land paperwork in 2017–18); estimates and quotes need checking against current local prices. Nothing here is legal, structural or professional advice; confirm permits and regulated work with someone qualified for your own site.